Which delivery method involves a single entity providing design and construction services under one contract?

Prepare for the Construction Manager in Training (CMIT) Test with essential content and question formats. Practice with flashcards and multiple choice questions that include hints and detailed explanations. Take your first step towards success!

Multiple Choice

Which delivery method involves a single entity providing design and construction services under one contract?

Explanation:
In design-build, one entity is contracted to provide both the design and the construction services under a single contract. This means the owner works with a single team responsible for the entire project from concept through completion, which promotes integrated planning, faster decision-making, and usually a shorter overall schedule since design and construction can overlap and feedback from buildability issues can be incorporated early. This is different from traditional design-bid-build, where design and construction are separate contracts with different firms, creating potential delays and more fragmented communication. It’s also distinct from CM-at-Risk, where a construction manager oversees the project and contracts separately with design professionals and the construction team, even though the CM plays a key role in cost and schedule—there isn’t one contract covering both design and construction by the same entity.

In design-build, one entity is contracted to provide both the design and the construction services under a single contract. This means the owner works with a single team responsible for the entire project from concept through completion, which promotes integrated planning, faster decision-making, and usually a shorter overall schedule since design and construction can overlap and feedback from buildability issues can be incorporated early.

This is different from traditional design-bid-build, where design and construction are separate contracts with different firms, creating potential delays and more fragmented communication. It’s also distinct from CM-at-Risk, where a construction manager oversees the project and contracts separately with design professionals and the construction team, even though the CM plays a key role in cost and schedule—there isn’t one contract covering both design and construction by the same entity.